Summary of Key Involvement / Specialization
A CIVIL ENGINEER WITH A MASTER DEGREE IN PROJECT MANAGEMENT. FIVE YEARS OF EXPERIENCE AS A
PLANNING MANAGER AND OVERALL 15 YEARS OF EXPERIENCE IN THE CONSTRUCTION INDUSTRY, LIKE
ROAD AND BUILDINGS, EXPERI-ENCE IN SITE SUPERVISION, CONSTRUCTION WORKS, TENDERING AND
EVALUATION. IN ADDITION TO THAT, HE IS WELL VERSED IN PLANNING AND SCHEDULING AND
DESIGNING WATER AND SEWAGE SYSTEMS AND OTHER STRUCTURES. SOUND KNOWLEDGE OF
ENGINEERING SOFTWARE’S. ALSO WELL VERSED WITH FIDIC CONDITIONS OF CONTRACTS. ADAPT AT
COORDINATING WITH BUILDING AND ENGINEERING PROFESSIONALS FOR EVERY PROJECT STAGE. ABLE
TO MULTITASK WITH EXCEPTIONAL SKILL IN FUNCTIONING WELL IN A HIGH-PRESSURE WORK
ENVIRONMENT.
PLANNING
The preparation and identification of critical path, resource levelling, logic link of networking diagrammed
SCHEDULING
Preparing the Gant chart programme with the specific project management software (Primavera AND/OR Microsoft Project)
MONITORING
In this aspect, the preparation and providing the progress report to the project team for the beneficial in project
monitoring with in line of PMBOK requirement and definitely to comply with contract requirement. Besides the conductive
of progress meeting with contractors are required as part of monitoring.
TIME CLAIM
To protect the LAD exposure due to dispute issues. To issue the notification of delay and exe-cute the Time Claim as EoT
claim. The varies of methodologies of Forensic delay analysis practices' (Windows Analysis; Time Impacted Analysis (TIA);
As-planned vs As-built Impacted; As-planned Impacted Analysis ; As built collapse analysis. And preparing the report/of
submission